Got ‘R’ Done

Obviously much has happened in the last few months.  Officially we moved in on April 1st and that’s no fooling.  Note the stone steps in the front, stone columns and the stone foundation.  The first picture shows the new gutters on the front with underground drainage going under the garage.20170507_16484220170410_09163720170510_094629

Progress 3-6-17

Happy Birthday Jeremy!   Take notice Jeff and Danny, Jeremy has started to re-claim the bricks saved from the old house.  Great effort!

Cultured marble showers are all installed.  Ceramic tile installation continues and is nearly complete on the first floor.  Cabinets are due for installation next Monday.  Steps and hand rails are installed to the second level, but need to have clear coat finish.  Painting is slowly progressing.

Hooking Up with Three Notch

Electrical service has been re-installed by Three Notch Electric.  The old power pole was removed and replaced with a taller pole and larger electrical transformer to service our house and our neighbors.  Instead of an overhead line to the house, workers run the electrical cable nearly six feet underground to the lodge.

Sorry Bob, they didn’t seem to have any respect for the azaleas, but i will nourish them back to health after their trampling.  The new 400 amp service is installed and we have power!